Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On July 5, the new modified asphalt plant of Shanxi Coking Group Co.
, Ltd.
tar processing plant was successfully started up and produced qualified asphalt products, marking the official operation of the new modified asphalt plant
.
The new modified asphalt mainly adopts flash evaporation and cooling low temperature forming technology, and the processing capacity of the modified asphalt unit is increased from the original 100,000 tons/year to 160,000 tons/year, which solves the bottleneck problem of the capacity release of the tar distillation unit
.
The device also solves the disadvantages of manual adjustment of the old device, can realize automatic control, and reduce labor costs
.
In addition, the device has advanced environmental management facilities, and the level of cleanliness and environmental protection has been comprehensively improved
.
The plant's new modified asphalt plant was constructed on May 28, 2021.
Through the transformation of the production process, a new tower furnace modified asphalt production device was built, the product layout was changed, the continuous and stable operation of the modified asphalt system was realized, and the tar processing system was added.
Economic benefits, it can fully process the medium-temperature asphalt produced by the tar distillation unit, and can generate an annual income of about 42 million yuan
.
It is reported that, in order to achieve smooth driving, the tar processing plant of the plant has studied in advance, optimized the driving plan, and prepared ideological mobilization for safe driving and various emergency measures in advance
.
During the driving process, the company's factory and workshop leaders adhered to the on-site guidance for driving, the technical personnel and central control personnel strictly controlled the process indicators, and the on-site personnel fully cooperated and operated in strict accordance with the driving plan to ensure the orderly start of the device
.