Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
China Petrochemical News Network reported on September 17, the transfer workshop 7401 tank area of Jinling Petrochemical's alkylbenzene plant hidden danger management project added flexible connection project to the roots of 4 5,000 cubic meters of storage tanks to ensure the absolute safety of production
According to the management requirements of continuously escalating safety and environmental protection standards, the original pipelines at the roots of the storage and transportation tanks in the transfer workshop of the alkylbenzene plant have hidden safety hazards, and decided to implement reforms to eliminate the hazards in a timely manner
The project started on August 18, with close cooperation and careful planning of all parties involved, to overcome difficulties such as difficult construction, high requirements, and tight schedules in the tank area, adopting methods such as low fire in the tank area, off-site prefabrication, and construction of each station, etc.
On September 17, the project, through the joint efforts of all parties involved in the construction, completed the construction ahead of schedule and put it into operation, eliminating hidden dangers and ensuring production safety