Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Sinopec News Network News On August 25, the two roasters of the Dalian Catalyst Project Department of the Tenth Construction Project were hoisted
The overall dimensions of the roasting furnace are 2.
Restricted by factors such as the large size of the equipment and the narrow hoisting work space, the equipment must be hoisted directly in front of the crane.
The minimum distance between the edge of the counterweight at the tail of the turntable and the edge of the steel column of the factory building is less than 120 mm during the swinging process of the rotating rod of the crane
In order to ensure the smooth progress of hoisting, the project department planned in advance, organized hoisting personnel to survey the measurement site several times, compiled detailed hoisting design plans based on the actual situation of the site, accurately checked all calculation parameters and construction details, and strictly planned the lifting path of equipment hoisting The hoisting preparation meeting was held the day before the hoisting, and the construction plan was accurately explained in detail, the responsibility was fulfilled, and the layout was accurately arranged, which ultimately ensured the efficient completion of the hoisting task, and was highly appraised by the supervisor and the owner’s on-site person in charge.
(Zhang Haibao)