Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
On June 5, 2020, the business negotiation of the 300,000-ton/year FDPE extrusion granulator for the million-ton ethylene project of Hainan Refinery and Chemical Company was successfully concluded, one month ahead of schedule, and the purchase price saved more than 12 million yuan compared with the estimated budget, and Compared with the purchase price of the same model of the brother company, after deducting the extra equipment configuration and spare parts for driving, the price has been reduced by more than 1.
5 million yuan
.
This equipment is one of the four extrusion granulators in the polyolefin plant of the million-ton ethylene project.
It belongs to the ultra-long cycle equipment.
It takes 24 months for foreign manufacturing and 18 months for domestic manufacturing.
It is a key supervision task in the "100-day attacking difficulties and creating benefits" action, requiring Hainan Refining and Chemical Company to complete the ordering work before June 30
.
Time is tight and tasks are heavy
.
In order to speed up the construction of the ethylene project, the Hainan Refining and Chemical Supply Department took the action of "one hundred days to overcome difficulties and create benefits" as the starting point, launched a labor competition for key equipment procurement, mobilized all employees to act quickly, strengthened communication and exchanges with suppliers, and squeezed around 4 units.
The granulator continuously conducts high-intensity video formal technical exchanges to ensure that the procurement progress of each long-cycle equipment is controlled within the plan
.