Categories
-
Pharmaceutical Intermediates
-
Active Pharmaceutical Ingredients
-
Food Additives
- Industrial Coatings
- Agrochemicals
- Dyes and Pigments
- Surfactant
- Flavors and Fragrances
- Chemical Reagents
- Catalyst and Auxiliary
- Natural Products
- Inorganic Chemistry
-
Organic Chemistry
-
Biochemical Engineering
- Analytical Chemistry
-
Cosmetic Ingredient
- Water Treatment Chemical
-
Pharmaceutical Intermediates
Promotion
ECHEMI Mall
Wholesale
Weekly Price
Exhibition
News
-
Trade Service
Recently, the acceptance team composed of the Inner Mongolia Autonomous Region Environmental Protection Agency and the Environmental Monitoring Station has passed the inspection and acceptance of the ultra-low emission retrofit project of Unit 2 in the Thermal Power Plant of Dalu Industrial Park
.
At the acceptance meeting, the acceptance team listened to the power plant’s report on the construction process of the 2# ultra-low emission retrofit project and the operation of the retrofitted unit.
After discussion, the acceptance team finally determined that the environmental protection equipment and data of the project met the ultra-low emission standards.
, Allowing the project to pass the acceptance
.
? It is understood that the ultra-low emission transformation project of unit 2 of the power plant was completed and put into operation in May 2018.
The desulfurization system adopts the desulfurization process of "calcium injection in the furnace + wet method behind the furnace", which heightens the original 2# absorption tower and removes dust.
The electric bag composite dust removal process is adopted, and the "low nitrogen combustion in the furnace + SNCR denitrification" process is adopted for denitration
.
At present, the emission concentrations of smoke dust, sulfur dioxide and nitrogen oxides from the total outlet flue gas of unit 2 of the power plant are better than the requirements of environmental protection indicators
.
.
At the acceptance meeting, the acceptance team listened to the power plant’s report on the construction process of the 2# ultra-low emission retrofit project and the operation of the retrofitted unit.
After discussion, the acceptance team finally determined that the environmental protection equipment and data of the project met the ultra-low emission standards.
, Allowing the project to pass the acceptance
.
? It is understood that the ultra-low emission transformation project of unit 2 of the power plant was completed and put into operation in May 2018.
The desulfurization system adopts the desulfurization process of "calcium injection in the furnace + wet method behind the furnace", which heightens the original 2# absorption tower and removes dust.
The electric bag composite dust removal process is adopted, and the "low nitrogen combustion in the furnace + SNCR denitrification" process is adopted for denitration
.
At present, the emission concentrations of smoke dust, sulfur dioxide and nitrogen oxides from the total outlet flue gas of unit 2 of the power plant are better than the requirements of environmental protection indicators
.